CR10 Updates

 

November 2006

The County Commissioners have selected Alternate 4 for the CR10 Realignment project.  The Commissioners and County Council will now determine the best funding solution.

 

January 2007

Letters have been sent to property owners who are most likely to lose their homes.  The letters are Notice of Intent letters and simply alert property owners that the County expects to purchase their property at a later date, and describes the relocation assistance they can expect and notifies them that a County hired appraiser will be making contact with them in the near future to begin the buying process.

 

April 2008

Purchase of homes required for the project is now complete.  Vacated homes are being removed by County forces to clear the right-of-way ahead of the construction project.  Purchase of land (not involving entire homes) is on-going and will continue through June.

 

Construction plans are 80% complete.  The CR10 and Six Span Bridge replacement projects have now been combined into a single project.  This is expected to result in more competitive construction bids.  Bids are planned to be advertised for the combined projects in August 2008, with the contract awarded in September.  Some construction work, notably the bridge piers, will begin in the fall of 2008 with the majority of CR10 construction taking place through spring, summer and fall of 2009.