** Construction is scheduled to
begin in the Spring of 2009.**
August
14, 2007 -- Bridge Field Inspection with
United
September
4, 2007 -- Asbestos Report Submitted
September
19, 2007 -- Condition Analysis Report
Submitted
January
11, 2008 -- Preliminary Plans Submitted
February
5, 2008 -- Preliminary Plan Review
meeting with United
February
12, 2008 -- Public Information Meeting
July 7, 2008 -- Final Plans Submitted
August 4, 2008 -- Highway Department sent out requests for RFP's (Request
For Proposal) for
Construction Inspection
August 29, 2008 -- RFP's for Construction Inspection submitted.
October 16, 2008 -- Bidding for this project has been put on hold.