Johnson
Scope:
The project will involve the replacement of the northbound
(eastern most)
Currently there are two structures present at the bridge site. The northbound structure, constructed in 1918 and the southbound structure constructed in 1992. The new structure will be constructed to the west of the structure constructed in 1992. The new structure would be designed to carry the southbound traffic while the 1992 structure would be converted to carry the northbound traffic. The new southbound structure would have a typical section matching the existing southbound structure.
In order to accommodate this proposed structure configuration, the existing
alignment of
Anticipated Design Timetable:
Design Consulting Engineer:
DLZ
Information/Updates:
·
This inspection encompasses an
overall review of the structure.
·
This inspection is scheduled to be
done every 2 years.
·
During this inspection, tension
members, connections, floor beams and floor beam hangers are reviewed in detail.
·
This inspection is scheduled to be
done every 2 years.
·
As a result of the I35 bridge
collapse in
·
Commissioners chose to proceed with
a 2-span steel girder option for the new structure
·
INDOT has hired a consultant,
Janssen & Spaans Engineering, Inc., to do fracture critical inspections of the
bridge every 3 months.
April 7, 2008 Posted project for bid