Anticipated Construction Timetable:

 

February 23, 2007        Proposals from engineering firms due

 March 26, 2007            Engineering firms interviewed/recommendation to Commissioners

May 1, 2007                 Design began

February 1, 2008          Design completion date (completion date subject to change based on changes in scope of the design)

May 21, 2008               Pre-bid meeting

April 7, 2008               Advertised for bids

June 16, 2008              Contract was awarded to Anlaan Corporation at a bid of $10,634,680.95  Construction is estimated to begin in September 2008 with an estimated completion in 2010.

September 12, 2008    Beardsley Ave. will be closed from September 24, 2008 to January 1, 2009. The closure will encompass approximately 300 ft. from the intersection of Johnson St. to the West.  More detail

October 23, 2008        Beardsley Ave. will remain closed until the Spring of 2009.  More detail