Des # 1401749

03-17-20

Current Status – a study of possible alternatives to improve the intersection was completed in February 2018. The preferred alternative is a peanut or elongated roundabout. Stage 1 design plans have been completed. A public informational meeting was held on Thursday, September 12, 2019 at 6:00 pm with public comments being requested by October 11, 2019. The final environmental document was approved January 2021. Right of way acquisition is scheduled for 2021-2022. The current project letting is scheduled for November 2022 with construction tentatively beginning in 2023.

Comments can be submitted to the Elkhart County Highway Department at eng@elkcohwy.org, 574-533-0538 or the Troyer Group at 574-259-9976.

CR 18, 13 & 115 Intersection Final CE

Presentation

Exhibits